Ebenezer Baptist Church Construction Schedule
Ebenezer Baptist Church  -  7094 Township Road 234  -  Logan, Ohio 43138  -  (740) 385-8411
Ministering to the Hocking Valley Since 1837
Listed below are tentative dates and major objectives for the construction
of our new church facilities
May 21 - June 1
Wall erection; truss erection and decking; start electical

May 24 - June 7:
Dry-in all segments of building; complete all mechanical rooms; major electrical rough-in; drywall ceilings;
start plumbing

June 7 - June 14
Roofing shingles & Flashings; HVAC ductwork, set air-handlers; electrical rough-in; rough-in plumbing

June 14 - June 23
Complete ductwork, substantially; complete roofing; complete building dry-in; secure plumbing rough-in
inspection

June 21 - June 27
Secure electrical rough-in inspection; secure HVAC rough-in inspection; secure plumbing inspection; secure
full framing inspection; insulate exterior walls; install windows

June 28 - July 7
Continue fire alarm system contract; resolve all issues; complete previous tasks; prepare for masonry;
continue electrical & HVAC

July 7 - July 14
Install block and stone; complete insulation; hang drywall; install siding and exterior trim; complete soffits and
eave trim; set aluminum sash

July 12 - July 19
Complete framing for drywall; complete framing at Sanctuary building; complete drywall at Education and
Office; complete all the exterior for painting; complete hanging of drywall

July 21 - July 28
Complete drywall finishing; begin painting in Educational; Drywall Sanctuary; begin trim out of interior; caulk
and paint exterior

July 28 - August 6
Doors, frames and hardware; complete sanctuary platform; complete sanctuary for painting; interior aluminum
and HM sash

August 4 - August 11
Begin hard flooring; lay-in ceilings; complete exterior painting; continue electrical

August 11 - August 18
Assemble cabinets; set cabinets and stain; complete electrical and panels; complete flooring at Educational;
install lighting and HVAC in lay-in

August 18 - August 25
Complete office area; complete exterior; completion of Educational areas

August  27 - August 31
Complete the Educational Building; complete the Sanctuary Building

September 3 - TBD
Complete for full occupancy; complete exterior and site